Mid June Roof Update
Date Published: June 20, 2022

The roof replacement is nearing completion apart from side panels for both the east and west transept. Replacement panels were delayed and are now scheduled for arrival in mid-July. There is still some painting and completion of the installation of gutters and downspouts. New louvers have been installed in the bell tower on the side where the chimney used to be. By the end of the month the scaffolding will be removed along with the temporary fence. Any other work will be done with the use of lifts. Other work will continue throughout the summer including the emergency exit, bell tower roof and restoration of the clerestory windows.

 

The bell tower before and after new louvers were installed.