Clerestory Window Update September 2022
Date Published: September 8, 2022

J & R Lamb Studios has done an outstanding job with the restoration of the clerestory windows.  The windows were removed from the dormers last month and taken back to their workshop. Restoration of the remaining windows should be completed in late September.  We anticipate installation of the glass windows in late October once the wood restoration of the dormer is finished.

Clerestory Windows July 2022 before restoration