The scaffolding, which is preventing installation of the remaining gutters and downspouts, should be coming down soon. The architect and contractor are working through a final list of items before the roof is considered complete. The replacement side panels on the east and west transepts, which are visible as the sections covered with white ice and water barrier, will be installed soon. Work on the restoration of the clerestory windows is expected to commence later in July. The windows will be removed for restoration and replaced with temporary inserts. The trim work around the windows will also be replaced or restored at this time. The fire-stair exit and bell tower roof work has not been scheduled but is expected to start later this summer.
Early July Church Building Update
Date Published: June 30, 2022